Drill holes before or after?

Flooring Forum

Help Support Flooring Forum:

This site may earn a commission from merchant affiliate links, including eBay, Amazon, and others.

conner172

Supporting Member
Supporting Member
Joined
Feb 11, 2025
Messages
1
Location
Minnesota
I'm installing a brand new floor over brand new floor joists for my remodeled bathroom. The question I have is, once I lay down the subfloor, do I drill the holes for the water supply pipes and drain pipes before I pour the self leveling concrete, or after I pour the self leveling concrete? There will be a 4" hole for the toilet flange, a 2-1/2" hole for the shower drain, a 2" hole for the sink drain, and 3/4" holes for the water supply pipes.
 
Drilling the holes through the subfloor first will be easier than trying to drill through leveler and subfloor. Drilling the holes after will make for easier smoothing of the leveler because you have no obstructions to work around.
 